Project to improve busy Aylesbury road continues

Project to improve busy Aylesbury road continues

Published by Dan Gooding at 5:49am 9th December 2019.

A 15-week project to upgrade a junction on one of Aylesbury's busiest roads starts today.

Preparations are happening to widen the Fowler Road junction on Oxford Road, which is now having £2.7 million spent on it.

This first phase will see a works compound set up before roadworks begin in January.

Phase one will see contractors set up a compound and build a new shared footway and cycleway on the southwest corner of Fowler Road .

These works will not affect traffic, although daytime footway closures between 8am and 5pm will be needed to allow preliminary work to continue for two weeks.

Following this phase, Monday 6 January sees the start of phase two: widening works on the Fowler Road junction approach at off-peak times (9.30am-3.30pm).

The final phase - resurfacing and lane markings - will be done at night, starting in March.

Project updates will be provided through e-bulletins and on the County Council website.